Warehouse racking
Buildings

Warehouses

Sprinkler design against the commodity classification and storage height.

At a glance

Hazard family
Buildings
Protected by
Sprinkler, Hydrant, Fire alarm
Designed to
NFPA 13, IS 15105, NBC 2016 Part 4
Ordinary hazard group 2 (general storage up to about 3.7 m)
8.1 L/min/m² over 139 m²

Design basis

Ordinary hazard group 2 (general storage up to about 3.7 m)
8.1 L/min/m² over 139 m²NFPA 13 — density/area
High-piled and rack storage
Set by commodity class and storage heightNFPA 13 — storage chapters

Standards that apply

  • NFPA 13Installation of sprinkler systems.
  • IS 15105Design and installation of fixed automatic sprinkler systems.
  • NBC 2016 Part 4Fire and life safety in buildings.

The risk

In a warehouse the fuel is the stock, and the way it is stored decides how fast a fire grows. High racking lets fire climb vertically between the loads; plastics and packaging burn hot and fast.

Large undivided floors, high roofs and full racks make a warehouse fire hard to reach, and the loss is usually the stock and the building together.

The scheme

Design to the commodity, not just the floor:

  • Sprinklers designed to the commodity class and storage height, with in-rack sprinklers where the racking calls for them.
  • Detection and alarm, with early warning to the people inside.
  • Hydrants around the building and within it where the code requires.
Protection concept for a warehouse: detection, sprinkler, hydrant layers

Systems that apply

Products used

Questions we are asked

Why does storage height matter so much?

Higher stacks let fire climb faster and hide it from ceiling sprinklers. Above a certain height, in-rack sprinklers or higher densities are needed.

Does changing what we store affect the sprinklers?

It can. A move to plastics or to higher racking can take the building outside its design basis, so the design should be checked.

Which sprinkler system suits an unheated warehouse?

A dry system, whose pipework holds air rather than water and so cannot freeze.

Related hazards

Track record

Projects on this hazard

All projects →

Considering us for a turnkey scope?

Send the hazard, the code and the site. Our engineers reply with a scheme and a price.